Contributors: Paul Young, Craig Whelton
Date published: 24 November 2026
Download as PDFRenewables projects: How to stop planning and procurement from complicating financial close
This article is based on recent webinar jointly produced by the firm and Locogen, a leading UK renewable energy consultancy that provides a wide range of expert consultancy services to clients who are developing, building or operating renewable energy projects. It includes contributions from Andrew Lyle, Locogen’s Founder and CEO; Steven Buckley, Principal Consultant; Iain McMillan, Head of Planning and Environment; and Sarah Sheriff, Director, Energy and Environment team, Virgin Money.
A recent series of webinars took one of the most important issues for developers – taking a project to financial close – and examined it from various perspectives, seeking both to analyse the underlying issues and to provide solutions. The events brought together experts from around the sector – with experience from the perspectives of engineers and technical advisers, finance, and legal – to provide a forensic 360-degree view of the issues. The first event focused on planning and procurement.
The contributors agreed that when projects experience difficulty achieving financial close, this is often due to decisions that were taken months or even years before. Onshore renewable energy projects are highly complex: developers have to address a range of challenges and balance a variety of risks. Timing each element to maximise the chance of success without sacrificing profitability involves making difficult decisions, and what was the best judgement at the time can become a barrier when seeking funding.
So, how can developers ensure that their projects have the best opportunity to progress through financial close successfully? Many insights emerged during the discussion, including:
Lenders want to get involved while there is still flexibility to make changes
Lenders need enough certainty to assess a project, but they do not want developers to wait until every contract is fixed. Approaching funders when negotiations are around 80–90% complete allows technical, legal and credit teams to test supplier strength, contractual interfaces, timelines, security and warranties, while there is still room to address risks without reopening the whole procurement process.
Sarah Sherriff, Director – Energy & Environment Team, Virgin Money: “We want to be able to get all of the key information out there, and make sure everything is in line with what’s expected, but to have a little bit of scope to do some negotiation or change some of the terms if needed to cover any risks that are thrown up.”
The race for equipment is forcing developers to procure earlier
Grid reform, connection dates and CFD windows are putting pressure on project programmes, while transformers, switchgear and batteries can have long lead times. Developers are therefore using early works agreements, letters of intent or direct orders before the main construction contract is settled. That can protect delivery slots and pricing, but it also introduces risks around interface, warranty and stranded equipment.
Bankability matters as much as cost
Choosing a faster or cheaper supplier can have downsides later. Lenders will examine its UK track record, financial strength, ability to honour warranties, and capacity to support or replace equipment over the project’s life. Tier 2 suppliers may offer shorter lead times and lower prices, but unfamiliar equipment, weaker balance sheets and limited local support can make lenders more cautious.
Steven Buckley, Due Diligence Team Lead, Locogen: “If Tier 2 suppliers don’t have a track record in the UK, developers need to address that, and I think the bank would expect their technical advisers to due diligence that as part of achieving financial close.”
Contracts can become funding blockers
A lender’s decision will depend on how each contract works within the wider delivery package. A supplier may be contracting through an unexpected group entity; liquidated damages may not match the project’s exposure; delivery dates may conflict with the programme; or early-procured equipment may sit outside the EPC contractor’s risk. These gaps can undermine the expected contractual wrap and force renegotiation, replacement orders or additional mitigations before funding proceeds.
Paul Young, Partner, Construction, Shepherd and Wedderburn: “If you are proposing a full EPC wrap to your lender but, in reality, that wrap has significant gaps … you’re going to have to get the lender comfortable with the risk exposure.”
Planning consent is only the starting point
A consent must support the project that will actually be built, operated and financed. Funders will review the permission and its conditions from a legal perspective and a technical one: they will check operational restrictions, reinstatement obligations, consent duration and land control. They will also expect pre-commencement conditions to have been formally discharged, with a clear record demonstrating that construction can begin without avoidable programme or cost risk.
Craig Whelton, Partner, Planning, Shepherd and Wedderburn: “Developers need to ask themselves: does the consent do what it says on the tin? Will the planning permission deliver a project that matches what we say the project is?”
Flexibility is becoming the most valuable feature of a planning consent
Early-stage layouts may not reflect the equipment ultimately required for grid compliance, fire safety or construction. Developers should therefore seek conditions that allow details to be agreed later, and should engage decision-makers early about acceptable flexibility. It can’t be assumed a planning authority will automatically treat changes as minor.
Iain McMillan, Head of Planning and Environment, Locogen: “When going through the planning process, have the discussion, seek to introduce flexibility wherever you can, and don’t make any assumptions that a condition will give you that flexibility, or that planning authorities will include that condition.”
BESS projects have unique challenges
Funding applications for BESS projects are facing greater scrutiny, particularly around fire safety, site access, water supply, water storage and drainage capacity. A highly flexible or outline design may no longer give decision-makers enough confidence. Developers may need to include infrastructure that is not ultimately required, because removing an approved element later is usually easier than seeking fresh permission for an omitted tank, access point or other safety measure.
Iain McMillan, Head of Planning and Environment, Locogen: “Whilst developers will want the flexibility and go in with a fairly basic design, it could come back to bite you down the line. It’s much easier to go in with a higher level of detail – add first and remove later.”
Small planning changes can create major funding delays
A change that looks modest in design terms can have disproportionate consequences for finance. If the as-built layout differs from the consent, the developer may need confirmation, a variation or even a new application. Because the outcome and timetable sit partly with the planning authority, an issue identified during due diligence can be difficult to quantify and impossible to resolve within an ambitious financial-close programme.
Key takeaways for developers
With all this in mind, what can developers do to minimise the procurement and planning legal risks to their projects?
From a procurement perspective, developers should pay close attention to how early works and equipment orders will fit into the final contractual structure. Programme pressure is a very real factor, of course, but it should be balanced against the risk of weakening the overall EPC wrap. If equipment with a long lead-time needs to be ordered before the principal contractor is appointed, the eventual contractor may refuse responsibility for it, particularly where warranties have started to run or storage has affected the equipment. Developers should therefore involve prospective contractors early, ensure early scopes are limited where possible, and confirm that suppliers and technical assumptions will be acceptable within the eventual delivery model.
Early payment arrangements also require careful legal and commercial analysis. Deposits can secure production slots and lock in prices, but developers need to consider whether payments can be recovered, whether equipment can be transferred to another project, and when title passes. Where substantial sums are paid before equipment reaches the UK, conventional security such as advance payment bonds may be expensive or unavailable, so alternative payment structures and security packages may be needed, particularly where the supplier has a limited track record or cannot provide strong parent-company support.
Planning presents a different type of legal risk: as it is a public law process, a defect cannot always be resolved through negotiation between commercial parties. If a condition was not discharged correctly, or consent does not cover the project being delivered, the developer may need confirmation or approval from the planning authority. And because the outcome and timetable are not entirely within the developer’s control, even seemingly modest issues can be difficult to quantify and so can disrupt financial close.
Finally, developers should test whether the consent supports the full project, including the red-line boundary, access, abnormal-load routes and off-site works. They should also maintain a clear paper trail showing that pre-commencement conditions have been discharged. Where design changes are needed, the correct planning route and likely timescale should be identified early. Bringing legal, technical, contractor and funder perspectives together before due diligence begins can reduce last-minute surprises and give all parties a clearer route to close.
Quotes have been lightly edited for clarity.