Clean Power 2030 targets: Ambition despite headwinds

The recent publication of the Clean Power 2030 Action Plan (CP30) highlighted the vital importance of the transition to clean power and the need for more offshore wind. 

This article discusses the challenges faced by Scotland’s offshore wind sector in meeting CP30 targets. 

First published in The Herald.

30 April 2025

Offshore wind farm

With ambitious targets set for the transition to net zero by both the UK and Scottish Governments, the role of Scotland’s offshore wind sector has never been more important. The recently published Clean Power 2030 Action Plan (CP30) reinforces the importance of the transition to clean power, and the urgency for more offshore wind, making it clear that delivery of the UK Government’s ambition of up to 50GW of offshore wind “requires a dramatic acceleration in progress compared to anything achieved historically and can only be achieved with a determined focus on pace and a huge collective effort across the industry.” 

The Scottish Government’s ambition is to increase offshore wind capacity by 11GW by 2030. To put that into context, there are currently nine fully operational offshore wind farms in Scottish waters, with a total installed capacity of 2.97GW. Scotland therefore needs to almost quadruple its offshore wind infrastructure within the next five years. Projects currently with consent and to be constructed or under construction will provide approximately 3.5GW of capacity. It is therefore evident that the dramatic acceleration referred to in CP30 is essential to meet the ambitious targets set by Westminster and Holyrood. CP30 recognises the urgency of progressing the current pipeline to meet 2030 targets, noting that “Accelerating delivery is exceptionally critical for offshore wind, where lead times for projects are often more than a decade. This means that all that can be deployed by 2030 has either already been consented or is in the development and consenting process.”

The ScotWind leasing round provided a promising boost to Scotland’s offshore wind sector, awarding seabed rights to 20 projects with a combined 27.6GW of capacity, and an additional 13 projects focused on reducing emissions from oil and gas production. 

Notwithstanding the pipeline that is there to be realised, the offshore wind industry is facing a number of challenges in achieving these targets: increasing costs, supply chain shortages, uncertainty over electricity market reforms and grid pricing increases, uncertainty over timing of upgrades required to the grid network to transmit the clean energy generated, and not least the time that it takes for projects to achieve consents. Taking the 4.1GW Berwick Bank project as an example, the offshore consent application was submitted in December 2022 and awaits a decision almost 2 and a half years on.

The Planning and Infrastructure Bill was introduced into Parliament in March 2025 and seeks to streamline the Scottish electricity consents process. This reform is welcome, but what the Bill falls short of doing (notwithstanding a key recommendation of the Winser Report, on which much of the package of reforms is based, was mandatory timeframes for all parties) is prescribing statutory timescales for consent determinations, which would bring the Scottish system into alignment with the equivalent consenting process south of the border. The Bill provides that the Secretary of State or the Scottish Ministers may make regulations specifying a time limit for consent determination. There is, however, no guarantee that such regulations would be forthcoming. One hopes that the Scottish Ministers will utilise the powers to create time limits for decision-making, in turn creating a renewed focus on consenting appropriate projects quickly and driving realisation of a sustainable Scottish offshore wind industry. However, as it currently stands, it remains to be seen whether the promise of improved efficiency will come to fruition and, critically, whether the necessary reforms will be in place in time to meet the ever-looming deadline to achieve 2030 targets.

Shepherd and Wedderburn is headline sponsor of All-Energy, the UK’s largest renewable and low-carbon energy exhibition and conference, taking place in Glasgow on 14–15 May 2025. Visit the All-Energy hub to find out more: shepwedd-allenergy.com.